docs(03-01): complete backend foundation plan — billing, encryption, HMAC OAuth, LLM key CRUD, usage aggregation

- Create 03-01-SUMMARY.md with full plan documentation
- Update STATE.md: progress 79%, 4 new decisions, session stopped at 03-01
- Update ROADMAP.md: Phase 3 plan progress (1/4 summaries)
- Update REQUIREMENTS.md: mark AGNT-07, LLM-03, PRTA-03, PRTA-05, PRTA-06 complete
This commit is contained in:
2026-03-23 21:38:10 -06:00
parent 3c8fc255bc
commit e0342f8ec1
4 changed files with 224 additions and 18 deletions

View File

@@ -83,7 +83,7 @@ Phases execute in numeric order: 1 -> 2 -> 3
|-------|----------------|--------|-----------|
| 1. Foundation | 4/4 | Complete | 2026-03-23 |
| 2. Agent Features | 6/6 | Complete | 2026-03-24 |
| 3. Operator Experience | 0/4 | Not started | - |
| 3. Operator Experience | 1/4 | In Progress| |
---