docs(09-01): complete E2E test infrastructure plan

- 09-01-SUMMARY.md: 29 tests across 7 flow specs, 3-browser coverage
- STATE.md: advanced to 94%, added 3 decisions, updated session
- ROADMAP.md: phase 9 in progress (1/3 summaries)
- REQUIREMENTS.md: marked QA-01, QA-05, QA-06 complete
This commit is contained in:
2026-03-25 22:38:45 -06:00
parent e31690e37a
commit 86a81ceabb
4 changed files with 196 additions and 14 deletions

View File

@@ -143,7 +143,7 @@ Phases execute in numeric order: 1 -> 2 -> 3 -> 4 -> 5 -> 6 -> 7 -> 8 -> 9
| 6. Web Chat | 3/3 | Complete | 2026-03-25 |
| 7. Multilanguage | 4/4 | Complete | 2026-03-25 |
| 8. Mobile + PWA | 4/4 | Complete | 2026-03-26 |
| 9. Testing & QA | 0/3 | In progress | - |
| 9. Testing & QA | 1/3 | In Progress| |
---